The process
From first call to first rent check.
Most ADUs are finished in 6–9 months. Here's exactly what happens at each stage — and what it costs.
- 01
Free feasibility call
1 day · FreeWe review your lot, zoning, setbacks, and goals. You leave the call knowing whether your property qualifies and a rough budget — no obligation.
- 02
Site visit & quote
1 week · FreeOn-site measurements, soil and utility check, and a written fixed-price proposal. You'll see every line item before signing anything.
- 03
Design & floor plan
2–3 weeks · $3K–$6K (credited to build)Choose from our pre-engineered models or customize. We finalize finishes, layout, and where the unit sits on your lot.
- 04
Permits & approvals
6–10 weeks · $8K–$15K (in proposal)We handle every permit, drawing, and city back-and-forth. You sign once; we navigate the rest.
- 05
Site prep & foundation
2–3 weeks · IncludedExcavation, utility trenching, and foundation pour. The first week the dirt actually moves is exciting.
- 06
Construction
12–16 weeks · IncludedFraming, roof, MEP, drywall, finishes. Weekly photo updates and a dedicated project manager. Most builds run 12–16 weeks.
- 07
Final inspection & keys
1 week · Final drawCity sign-off, walkthrough, and a punch list we resolve before final payment. We help you list and price for rent if you want.
Ready to start with step 01?
It's a free, 30-minute call. You'll leave with a clear yes/no and a real budget range.